2024 Referendum Project Updates
Each month, we will be providing an update to the design and construction progress of the 2024 referendum on our district 2024 Referendum web page.
These updates will provide an overview of recently completed work and next steps. All monthly updates also will be archived on the site to provide a transparent timeline of progress.
January 2025 update
Design and construction updates:
Planning work is underway by the Architecture and Construction Team to establish priorities, gather site and building information, assemble team members and understand scope/schedule.
Scanned existing building plans
Completed 3D virtual tours
Completed 3D Revit model of all buildings
Placed engineers under contract
Assigned architects and project specialists team
Held owner meetings
Reviewed schedule/scope
Started site plans for summer 2025 playground improvements
Met with City to discuss review process
What’s next:
Convene communications team
Create and deploy transparency tracker
Finalize Summer 2025 project list
Example of birds-eye view photo taken during building scan reports of Eisenhower, Fisher, Jefferson, Madison, Roosevelt, and Washington buildings.